Door Model Delivery Sequencing: Shipping by Floor and Room Type to Speed Up Installation
Door delivery sequencing means shipping and labelling hotel doors in the order the building will be fitted out. This guide explains how to split shipments, mark leaves and coordinate with site teams.
Door delivery sequencing is the practice of manufacturing, packing and shipping doors in the order your installers will need them, rather than in whatever order is most convenient for the factory. For a hotel with hundreds of openings, it can be the difference between a smooth floor-by-floor handover and a site cluttered with unidentified crates. This guide shows how to plan phased door shipments, label leaves clearly and align deliveries with your construction programme.
Why sequence matters more than it seems
A hotel door package is rarely uniform. It usually includes guest room entrance doors, bathroom doors, wardrobe doors, connecting doors, suite entrances and service doors, often in different sizes, handings and fire ratings. If everything arrives mixed in one lot, the site team spends days sorting before a single door is hung.
Sequencing solves three practical problems:
- Site storage: hotel sites rarely have space to store a full door order for the whole building.
- Handling damage: every time a leaf is moved to find another one, the risk of edge chips and scratches rises.
- Installer productivity: crews work faster when the next floor's doors are already identified and staged.
Start with the door schedule
Sequencing is only as good as the schedule behind it. Each opening needs a unique reference that links the door, its frame, its hardware set and its location. At minimum, your schedule should show:
- Floor, room number and opening type (entrance, bathroom, wardrobe, connecting)
- Leaf size and thickness, with metric dimensions first and imperial in brackets where needed, for example 900 x 2100 mm (35.4 x 82.7 in)
- Handing and swing direction
- Finish and model name
- Fire rating or acoustic requirement, if any
- Hardware set and lock preparation details
If the schedule is incomplete, the factory cannot label accurately. It is better to resolve open questions before production than to correct labels on site.
Decide how to split the shipments
There is no single correct split. The right approach depends on your construction programme, the number of containers and the logistics route. Common strategies include:
By floor or zone
This is the most intuitive method for a multi-storey hotel. Doors for the first floors to be fitted out are shipped first, and later floors follow. It works well when the structure is completed progressively and finishing trades move upward or downward in a predictable pattern.
By room type
If one room type is being used for a show room or early handover, you may want all doors for that type first. This also helps when a mock-up room has been approved and the remaining identical rooms can follow without waiting for other areas.
By wing or building
For resorts and villa developments with multiple buildings, splitting by building keeps shipments aligned with separate construction teams and avoids long-distance on-site transfers.
Combined approach
Many projects use a hybrid: a first shipment for the mock-up and pilot floor, then regular shipments by floor group, and a final shipment for public areas, service doors and spares. Discuss this with your manufacturer early so production planning reflects it.
Build the shipping plan around the programme
Work backwards from the date each floor is ready for door installation, not from the date the building opens. Allow time for production, packing, transit, customs clearance and inland delivery. Transit and clearance time varies by destination and route, so confirm it with your freight forwarder rather than relying on assumptions.
Shipping terms also affect how sequencing is handled. Under EXW or FOB, you or your forwarder control the main carriage and need to coordinate loading dates with the factory. Under DAP, the supplier arranges delivery to the named place, but you still need to confirm unloading access, site storage and receiving hours.
Where several containers are involved, agree the loading order. Doors needed first should be loaded so they come out first, or be placed in a dedicated container, so the site does not need to unload everything to reach them.
Labelling: the system that makes sequencing work
Door labelling by floor and room is what turns a shipment into an installable package. Good labelling is simple, consistent and visible without unpacking.
What to put on each leaf label
- Opening reference matching the door schedule
- Floor and room number
- Door type and model name
- Handing (left or right) and swing direction
- Dimensions and thickness
- Hardware set reference
Label the packaging as well
Each package should carry the same reference on the outside, so crews can identify doors without opening the wrapping. For grouped bundles, add a floor-level label and a package number, for example 3 of 12. Colour-coded tapes or tags for floors can help on busy sites, as long as the code is documented in the packing list.
Keep frames, leaves and hardware matched
Frames, architraves and loose hardware should carry the same opening reference as their leaves. A common cause of delay is a correct door arriving with a frame that has been shipped in another lot. If frames and leaves travel separately, make sure both are scheduled for the same floor release.
Use a protected label position
Labels should be placed where they will not damage the finished surface. Avoid applying adhesive labels directly to lacquered or veneered faces. Ask the factory to put them on protective packaging or on a hidden edge, and to confirm that residue will not be left behind.
Packing for build order
Packing should reflect the sequence, not just protect the goods. Doors for one floor are best grouped together, with the heaviest or largest leaves positioned for safe handling. Mixed pallets containing multiple floors make it difficult to release doors progressively.
Protective materials such as edge guards, film and corner protection should be consistent across packs, so installers know what to remove and when. Surface protection film should generally stay on until final cleaning, unless the site requires otherwise.
Plan storage and handling on site
Even a perfect shipment can be spoiled by poor storage. Agree these points before delivery:
- Dry, enclosed storage: wooden doors should not be left outdoors or in damp areas, because moisture can lead to swelling or warping.
- Flat or upright rules: follow the manufacturer's guidance for how leaves should be stacked or stood.
- Floor staging: where possible, move each floor's doors to the relevant level just before installation, not weeks earlier.
- Lift and access limits: check lift dimensions and corridor widths so packaged leaves can be moved without forcing them.
A short receiving check at each delivery also helps. Count packages against the packing list, inspect for visible damage and record any issues with photographs before the crates are opened further.
Coordinate the people involved
Sequencing is a communication task as much as a logistics one. The parties who need to align are the factory, your freight forwarder, the main contractor, the door installer and, where relevant, the lock and hardware suppliers. A short shared document that lists floor release dates, shipment numbers and contact names avoids misunderstandings.
If electronic locks are being fitted, check that preparation details such as routing and cable paths are agreed before production. Otherwise, a sequenced delivery can still be held up while a hardware question is resolved.
Common sequencing mistakes to avoid
- Shipping everything in one lot because it looks cheaper per container, then paying later in site labour and damage.
- Changing the floor order late in the programme without informing the factory.
- Using room names on labels that differ from the contractor's drawings.
- Sending frames and leaves in different shipments with no clear link.
- Forgetting spare doors and hardware, which then arrive mixed with the main order.
A simple sequencing checklist
| Stage | What to confirm |
|---|---|
| Schedule | Unique opening references, handing, finish and hardware set |
| Shipment plan | Split by floor, zone or room type, with target site dates |
| Labelling | Leaf, frame and package labels using the same references |
| Packing | Grouped by release, protected edges, clear package numbers |
| Logistics | Incoterms, loading order, customs documents and site access |
| Site | Dry storage, receiving checks and staged movement to floors |
Next step
Door delivery sequencing works best when it is agreed before production starts. If you are planning a new hotel or a renovation, send us your door schedule and construction programme. We will review the openings with you and suggest a shipment split, labelling approach and packing method that suits your project.
Sıkça Sorulan Sorular
What is door delivery sequencing?
It is the planned release of doors in the order they will be installed, usually by floor, zone or room type. Each shipment and package is labelled so installers can identify every leaf quickly and work without sorting or searching.
Is it better to ship all hotel doors at once or in phases?
It depends on site storage, programme and container count. A single shipment can reduce freight handling, but phased door shipments usually reduce storage needs, handling damage and sorting time. Many projects combine a pilot batch with later floor-based lots.
What should be written on a hotel door label?
Include the opening reference from the door schedule, floor and room number, model, handing, dimensions and hardware set. Place the label on protective packaging or a hidden edge so it does not damage the finished surface.
How do Incoterms affect sequenced deliveries?
Under EXW or FOB you coordinate main transport and loading dates, while under DAP the supplier arranges delivery to the named place. In every case, confirm loading order, site access and receiving hours so each lot arrives when needed.
When should I send my door schedule to the factory?
Send it before production planning begins, ideally with your construction programme. An early, complete schedule lets the factory plan batches, prepare accurate labels and avoid corrections that could delay a floor release.