Console Table Procurement for Hotel Conversions: Retrofitting Existing Buildings Into Hotels
Converting an office, apartment block or heritage building into a hotel means irregular rooms and tight programmes. This guide shows how to procure console tables that fit real geometry and arrive on time.
Hotel conversion furniture console orders behave differently from those in purpose-built hotels. Walls are rarely square, ceilings and floors vary, and structural columns sit where a designer would never have placed them. If you are procuring console tables for an office to hotel conversion, the main task is to match each piece to measured reality rather than to the drawing alone.
This guide explains how to survey, specify and schedule console tables for converted buildings, and how to work with a made-to-order manufacturer so that pieces fit on the first installation attempt. Palmiye produces custom hospitality furniture to project drawings in Istanbul and ships worldwide, so the notes below reflect how export orders are typically planned.
Why conversions are different from new-build hotels
In a new hotel, room types repeat and the structure is designed around them. In a building conversion fit-out, the shell comes first and the hotel has to adapt. That changes how you buy furniture.
- Irregular room geometry: corridors that taper, niches of different widths, bay windows and chamfered corners.
- Existing services: risers, radiators, sockets and fire equipment that cannot always be moved.
- Compressed schedules: owners often convert because they want a faster opening, so furniture lead time sits close to the critical path.
- Fewer identical rooms: a single floor plate may produce several room variants, which tempts you to order many one-off sizes.
Where console tables are used in converted hotels
Console tables are useful in conversions because they are slim, flexible and visible. They also solve awkward spaces that fixed joinery would take longer to build.
- Reception and lobby: as a feature piece against a column or a retained heritage wall.
- Corridor and lift lobby recesses: where an office core leaves an odd alcove.
- Guest room entries: slim models in the short passage between door and bed.
- Suite living areas: behind a sofa to divide the space in large former apartments.
For dimension ranges by space type, see our wider guidance on console table sizing; here we focus on how conversion conditions change the specification.
Step 1: Survey before you finalise any size
Drawings of existing buildings are often out of date. Measure the actual locations where each console will stand, and record more than width and depth.
- Measure width at floor level, at table height and at the top of the skirting, because walls may lean.
- Note skirting board depth and profile, as they affect wall clearance.
- Check floor level over the footprint of the legs; older slabs and screeds can slope.
- Mark socket, switch, radiator and sprinkler positions near the piece.
- Confirm the wall type, since fixing a wall-mounted console to a drywall partition differs from fixing to masonry.
Photograph each location with a tape measure in frame. Clear photos let a factory understand conditions that a drawing cannot show.
Step 2: Group locations into a few size families
One-off sizes for every alcove increase drawing work, sampling and cost. A better approach is to group similar locations into a small number of families, then absorb minor differences with design details.
- Choose two or three lengths that cover most locations.
- Keep depth constant within a family so the profile looks consistent along a corridor.
- Use filler strips, scribed side panels or adjustable feet to deal with small gaps.
- Reserve true bespoke sizes for the few high-visibility positions, such as the lobby.
This keeps the visual language coherent and shortens the approval stage, which matters when time is tight.
Step 3: Design for tolerance, not perfection
In a converted building, a rigid design that needs a perfectly flat wall and a level floor will cause problems on site. Ask the manufacturer to build tolerance into the piece.
- Adjustable feet or levelling glides for sloping floors.
- Scribe allowance on the back edge or side panels so the piece can be trimmed to an uneven wall.
- Skirting notches or a slight setback so the table sits flush against the wall.
- Slim back panels that protect the wall and allow cable routing where services cannot be moved.
Scribing on site needs a skilled installer and a little extra time on the programme, so agree in advance who will do it and with what tools.
Step 4: Check access and handling routes
Converted buildings often have narrow stairs, small lifts and tight turns that were never designed for furniture deliveries. A console table that fits its final position may still not fit the route to it.
- Measure lift car interiors and door openings, not only corridors.
- Ask whether long pieces can be supplied with detachable legs or in separate top and base sections.
- Plan the delivery sequence so that furniture enters before final wall finishes and flooring protection are compromised.
- Confirm where packed pieces can be stored on site while other trades finish.
Step 5: Compress the schedule without cutting corners
Lead time depends on materials, finish, quantity and approvals, so we do not quote fixed durations in a general guide. What you can control is how quickly decisions are made.
- Release the survey data early. Even a partial set lets drawing work begin.
- Approve a single sample. One console in the main finish can confirm proportions, colour and details for the whole order.
- Fix the finish early. Colour changes after sampling are one of the most common causes of delay.
- Phase deliveries. Ship public areas and the first floors first, then follow with later floors as they are completed.
- Keep one decision-maker. Conflicting comments from owner, operator and designer slow approvals.
If your opening date is fixed, tell the factory at the first enquiry. It can then advise which options affect production time and which do not.
Fire and safety considerations in converted buildings
Buildings converted from offices or other uses may have escape routes and corridor widths that were set for a different occupancy. Console tables in corridors and lift lobbies must not reduce clear width or obstruct escape routes. Requirements vary by country and by building type, so confirm them with your fire consultant or local authority before fixing positions.
Also ask whether fire-retardant boards, finishes or fabrics are required for any furniture in public areas. Raising the question early avoids redesign later.
Material choices that suit conversion projects
Because walls and floors are imperfect, robust construction is more useful than delicate detailing.
- Veneered panels with solid wood edges give stable tops and resist warping across long spans.
- Solid wood legs or frames tolerate repeated handling in busy corridors.
- Protective lacquers suit high-traffic public areas, while oil finishes may fit quieter suites where repair is easier.
- Wall-mounted designs keep floors clear but require a suitable substrate, so check wall construction before choosing them.
Documents to prepare for an accurate quotation
The more complete your brief, the more reliable the estimate. For a conversion project, send:
- Floor plans marking each console location and a location code.
- Photos and measurements from the survey.
- Preferred wood species, finish and any colour references.
- Quantity per size family and the target delivery sequence.
- Destination country, preferred Incoterm such as FOB or DAP, and any site access limits.
- Fire or compliance requirements for the destination.
Pieces are made to order from your drawings or from a reference photo that we convert into shop drawings, then approved by you before production starts.
Common mistakes in conversion furniture procurement
- Ordering from architectural drawings without verifying dimensions on site.
- Specifying too many one-off sizes.
- Leaving no tolerance for uneven walls or floors.
- Forgetting lift and stair access.
- Choosing the finish late and then changing it after sampling.
Conclusion
A successful hotel conversion furniture console order depends on measured data, a small number of size families and details that forgive imperfect buildings. Add a clear approval path and phased delivery, and you protect both the budget and the opening date.
If you are planning a building conversion, send us your floor plans, survey photos and target schedule. We will review the project and come back with design suggestions, an estimated lead time and shipping options to your location.
Sıkça Sorulan Sorular
Can console tables be made for irregular rooms in a hotel conversion?
Yes. Made-to-order pieces can be sized to measured niches and fitted with adjustable feet, scribe allowances or skirting notches. Send survey photos and dimensions so the shop drawings reflect real conditions, then approve a sample before production.
How many different sizes should I order for a converted building?
Keep the number small. Group similar locations into two or three size families with constant depth, and use filler details for minor differences. Reserve fully bespoke sizes for high-visibility spots such as the lobby.
Do you ship console tables for hotel conversions worldwide?
Yes, Palmiye produces in Istanbul and ships to projects worldwide. Shipping terms such as FOB or DAP, packing method and delivery phasing are agreed per project, depending on destination and site access.
How can I shorten lead time on a conversion project?
Share survey data early, fix the finish before sampling, approve one sample and phase deliveries by floor. Actual lead time still depends on quantity, materials and approvals, so the factory confirms it after reviewing your brief.
Do console tables in converted hotel corridors need fire checks?
Often yes. Corridor widths and escape routes in converted buildings may differ from new hotels, and some countries require fire-retardant materials in public areas. Confirm requirements with your fire consultant or local authority before fixing positions.