How to Write a Technical Specification for Vitrines When Tendering to Several Factories
A clear vitrine technical specification makes every factory quote the same product, so price differences reflect real value rather than guesswork. This guide gives you a section-by-section outline you can adapt for your own tender.
A vitrine technical specification is the document that tells every bidding factory exactly what to build, test, pack and deliver. When you tender to several suppliers, it is the only thing that keeps the quotes comparable. Without it, one factory prices a 18 mm veneered board with soft-close hinges, another prices a thinner melamine board with basic hinges, and you end up comparing two different products.
This guide gives you a practical outline for writing that document. It works for single custom vitrines and for large bulk programmes, and it can be sent to manufacturers anywhere in the world.
Why a Written Specification Matters in a Tender
Photos and a rough sketch invite interpretation. Each factory fills the gaps with its own assumptions, and those assumptions drive the price. The lowest quote is often simply the one that assumed the least.
A good specification does three things:
- It makes every supplier price the same scope, materials and quality level.
- It reduces clarification emails and delays during the bidding period.
- It becomes the reference document for sample approval, inspection and any later dispute about quality.
Recommended Structure of the Specification
Keep the document short enough to be read but detailed enough to leave little room for guessing. A structure of eight sections usually works well.
1. Project overview and scope
State what the vitrines are for (hotel lobby, retail corner, restaurant, residence), the number of pieces, the destination country and the target delivery window. Say whether you want supply only, or supply with installation and packing for export.
If there are several models, give each one a code, such as V-01 or V-02, and use that code in every later section and in the drawings.
2. Dimensions and tolerances
List overall width, depth and height in millimetres, with inches in brackets if your team uses them, for example 900 mm (35.4 in). Add the internal shelf spacing, door opening size and any plinth or base height.
Specify what tolerance you accept. A line such as "overall dimensions to be within an agreed tolerance stated by the factory" forces bidders to declare their standard. Also state whether dimensions are final or subject to site measurement.
3. Construction and core material
Describe the carcass material and thickness: MDF, plywood, particle board or solid wood frame. State the board grade and, where relevant, the emission class or fire performance required in the destination market.
Also cover the back panel, the shelf supports, and how panels are joined (dowels, cam fittings, screws or a combination). These details change both strength and cost, so they should not be left to the bidder.
4. Surface finish and colour
Say clearly whether the finish is wood veneer, melamine, HPL, lacquer or paint. For veneer, name the species, cut and grading expectation. For paint or lacquer, give the colour reference (RAL, NCS or a physical sample) and the sheen level: matte, satin or gloss.
Request that each factory confirms how colour will be approved before production. A finish sample sent by courier is the safest route for a bulk order.
5. Glass specification
Glass is often where quotes diverge most. Specify the type (tempered, laminated, tinted, mirrored or low-iron), thickness in millimetres, edge treatment (polished, seamed, bevelled) and the position of each glass element: doors, side panels, top and shelves.
For public spaces, state any safety requirements, such as laminated glass or protective film. Ask bidders to confirm the maximum shelf span their proposed glass thickness can carry.
6. Hardware, locks and lighting
List hinge type and brand level, door closing mechanism (soft-close or standard), handles or handleless profiles, and lock type. If you need a master-key system across many cabinets, say so, because it affects both hardware cost and production planning.
For lighting, describe the LED type, colour temperature, switching method, power supply location and how the transformer is accessed for service. Avoid the vague phrase "LED lighting included"; it allows very different products to be quoted.
7. Packing, labelling and shipping terms
Define the packing method: cartons with corner protection, foam, wooden crates for glass, and whether the product ships assembled or flat-packed. Mention that timber packing should follow the import rules of the destination country.
State the Incoterm you want quoted (EXW, FOB, CIF or DAP) and the named port or delivery address. Without this, one bidder may quote ex-works and another delivered, and the totals cannot be compared.
8. Samples, inspection and commercial terms
Describe whether you require a pre-production sample, how long you will take to approve it, and what inspection you expect before shipment (photos, video call, third-party inspector). Ask for quoted validity period, payment terms, production lead time and warranty or defect-handling terms, each as a separate line.
Attach Drawings and Reference Images
A specification works best alongside a dimensioned drawing for every model. Even a simple front and side view with measurements removes many questions. If you only have reference photos, mark which features must be copied and which are open to the factory's suggestion.
Number the drawings and refer to them in the specification so there is no doubt which version applies.
Use a Price Comparison Table
Do not accept free-form quotations if you can avoid it. Send a simple quotation sheet and ask every factory to fill it in. A layout like the one below makes comparison straightforward.
| Line item | What bidders should state |
|---|---|
| Unit price per model | Price for each model code in a stated currency |
| Materials | Board type, thickness, finish, glass type and thickness |
| Hardware | Hinge, lock and runner type |
| Packing | Method and whether included in price |
| Incoterm | Term and named place |
| Lead time | Days from sample approval or order confirmation |
| Validity and payment | Quote validity and payment schedule |
If a bidder proposes an alternative material or hardware, ask them to quote your specification first and list the alternative as a separate option. That way you compare like with like and still see useful ideas.
Allow Questions and Keep the Playing Field Level
Set a deadline for questions and send every answer to all bidders, not just the one who asked. This keeps the process fair and often reveals gaps in your own document.
It is also sensible to ask each factory for a few photos or videos of similar work and a brief description of its production capacity. Treat this as supporting information rather than a substitute for the written quote.
Common Specification Gaps to Avoid
- Missing glass thickness or glass type.
- No Incoterm or delivery location.
- Colour described by name only, with no reference code or sample.
- No statement on tolerance or assembly format.
- Quantity given as a total without a split by model.
- No sample or approval step before bulk production.
Evaluating the Quotes
Once the sheets come back, check scope first and price second. Look for lines left blank, materials that differ from your specification and exclusions hidden in the notes. A quote that looks cheaper may leave out packing, lighting or glass protection.
Then compare lead time, payment terms and sample policy. The best choice is usually the supplier that answered clearly, matched your document and communicated promptly, not only the one with the lowest figure.
Next Step
If you are preparing a tender for custom or bulk vitrine orders, send us your drawings, quantities and destination. We will review them, point out any missing specification details and prepare a quotation based on your document, with options for materials, glass and shipping to your market.
Sıkça Sorulan Sorular
What should a vitrine technical specification include?
It should cover scope and quantities, dimensions with tolerances, core material, finish and colour reference, glass type and thickness, hardware and locks, lighting, packing, Incoterm, sample approval and commercial terms. Attach dimensioned drawings so every bidder prices exactly the same product.
How do I compare vitrine quotes from different factories?
Send the same specification and a standard quotation sheet to every bidder. Compare scope first, including materials, glass, hardware, packing and Incoterm, then look at price, lead time and payment terms. Ask for alternatives as separate options so the base quotes stay comparable.
Do I need drawings for a vitrine RFQ?
Drawings are strongly recommended. A simple front and side view with measurements removes most questions. If you only have reference photos, mark which features must be copied exactly and which details the factory may suggest, so quotes stay consistent.
Which Incoterm should I request in a vitrine tender?
It depends on how much of the logistics you want to manage. FOB suits buyers with their own freight forwarder, while CIF or DAP suit buyers who prefer a delivered price. Whatever you choose, ask every bidder to quote the same term and named place.
Should I ask for a sample before bulk production?
For custom or large orders, yes. A pre-production sample lets you check dimensions, glass, finish colour and hardware before committing to the full quantity. State in the specification how long approval will take, as this affects the production schedule.